M/S Bhumi Developers v. State of U.P & Anr.
Case at a glance
- Order date
- 18 May 2023
- Bench
- ASHWANI KUMAR MISHRA, VINOD DIWAKAR
- Neutral citation
- 2023:AHC:109139-DB
Provisions considered
Judgment
Though a notice issued under Section 10 of the U.P. Urban Planning and Development Act, 1973 prohibiting the petitioner from raising construction is challenged, but at the time of hearing of the matter, learned counsel for the petitioner confines his relief to a direction upon the Greater Noida Authority to accord consideration to his application for sanction of construction. The map along with requisite application is stated to have been submitted on 1.4.2023. Mrs. Anjali Upadhya appearing for the Greater Noida Authority states that in the event petitioner has submitted an appropriate application for grant of permission to raise construction, the second respondent would accord consideration to it, in accordance with the applicable regulations. In view of the stand so taken, we dispose of this writ petition permitting the petitioner to approach the second respondent, annexing all relevant details along with application submitted by him, along with a certified copy of this order, within a week from today. The second respondent shall ensure that petitioner's application is examined in light of the applicable provisions, by passing a reasoned order, within a further period of six weeks, thereafter. Order Date :- 18.5.2023 Anil ANIL KUMAR PATEL High Court of Judicature at Allahabad
Questions this judgment answers
Which statutory provisions did this judgment involve?
U.P. Urban Planning and Development Act, 1973 — s. 10.
Which court decided this case, and when?
Allahabad High Court, on 18 May 2023. The bench was ASHWANI KUMAR MISHRA, VINOD DIWAKAR.
Precedent status how later indexed judgments have treated this case
No known negative treatment found in the Courts & Cases corpus.
This is a result about the indexed corpus, not a finding that the judgment remains good law. Coverage may be incomplete.