✦ Kerala High Court · 05 Dec 2012

K.S. SELVAN v. KERALA STATE ELECTRICITY BOARD

Case Details Kerala High Court · 05 Dec 2012
Court
Kerala High Court
Decided
05 Dec 2012
Bench
—
Length
1,043 words

Acts & Sections

Cited in this judgment

Summary

A structured summary for this judgment hasn’t been prepared yet. The full text is below.

Precedent status

No treatment data yet for this judgment in the Courts & Cases corpus.

Absence of data is not a statement about the judgment’s standing — the corpus covers only judgments we index and link with cited evidence.

Why is this linked?

Original judgment text

BY ADV. SRI.A.D.SHAJAN RESPONDENTS: -----------------

1. KERALA STATE ELECTRICITY BOARD VYDHYUTHI BHAVAN, PATTOM, THIRUVANANTHAPURAM REP. BY ITS SECRETARY.

2. THE CHIEF ENGINEER, COMMERCIAL AND TARIFF, VYDHYUTHI BHAVAN, PATTOM THIRUVANANTHAPURAM.

3. THE ASSISTANT EXECUTIVE ENGINEER, ELECTRICAL MAJOR SECTION, KOZHINJAMPARA, PALAKKAD.

4. THE ASSISTANT ENGINEER, ELECTRICAL MAJOR SECTION, VELANTHAVALAM, PALAKKAD DISTRICT.

5. KERALA STATE ELECTRICITY REGULATORY COMMISSION, 30, PARAMESWARA BHAVAN BELHAVEN GARDENS, KAWDIAR, THIRUVANANTHAPURAM REP. BY ITS SECRETARY.

6. STATE OF KERALA, REP. BY ITS SECRETARY TO GOVERNMENT, POWER DEPARTMENT SECRETARIAT, THIRUVANANTHAPURAM R1 TO 4 BY ADV. SRI.P.P.THAJUDEEN, SC, K.S.E.B R1-R4 BY ADV. SRI.SAJEEVKUMAR K.GOPAL,SC,KSEB BY ADV. SMT. P MAYA, GOVERNMENT PLEADER THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 05-12-2012, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING: WP(C).No. 29073 of 2008 (J) : 2 : APPENDIX PETITIONER'S EXHIBITS: EXT.P1 : TRUE COPY OF THE NOTICE NO.BB/ES/VLM/APTS BILL/2008-09/89/4-9-08 DATED 04.09.2008 ISSUED BY THE 4TH RESPONDENT TO THE PETITIONER. EXT.P1(a) : TRUE COPY OF THE INVOICE DATED 04.09.2008 ISSUED BY THE K.S.E. BOARD. EXT.P2 EXT.P3 EXT.P4 EXT.P5 : TRUE COPY OF THE BOARD ORDER NO.BO(PB) NO.1292/2002/(PLG.COM.4206/01 DATED 18.09.2002) : TRUE COPY OF THE BOARD ORDER NO.BO(FM) DATED NO.368/2008(DPC1/C-G1/182/2007) 07.02.2008. : TRUE COPY OF THE JUDGMENT IN O.P. NO. 26408/00 DATED 10.02.2006 IN THE HON'BLE HIGH COURT OF KERALA, ERNAKULAM. : TRUE COPY OF THE ORDER IN R.P. NO. 974/06 DATED 28.11.2006 IN THE HON'BLE HIGH COURT OF KERALA, ERNAKULAM. EXT.P6 : TRUE COPY OF THE OBJECTION DATED 27.09.2008 SUBMITTED BY THE PETITIONER. RESPONDENTS' EXHIBITS: NIL //TRUE COPY// P.A. TO JUDGE B.P. RAY, J. - - - - - - - - - - - - - - - - - W.P.(C) No. 29073 of 2008 - - - - - - - - - - - - - - - - Dated this the 5th day of December, 2012. JUDGMENT Heard the learned counsel for the petitioner and the learned Standing Counsel for the Kerala State Electricity Board.

2. The issue involved in this case is squarely covered by the decision in Executive Engineer and another v. Sitaram Rice Mill reported in (2010 (4) KHC 1) wherein the Apex Court in paragraphs 44 and 46 held as follows: relatable “44. Minimum energy charges are to be levied with reference to 'contract demand' at the rate prescribed under the terms and conditions. These clauses of the agreement clearly show that the charges for consumption of electricity are directly sanctioned/connected load and also the load consumed at a given point of time if it is in excess of the sanctioned/connected load. The respondent could consume electricity upto 110 KVA but if the connected load exceeded that higher limit, the category of the respondent itself could stand changed from 'medium industry' which will be governed by a higher tariff. 45. xxxxx 46. On the cumulative reading of the terms and conditions of supply, the contract executed between the parties and the provisions of the 2003 Act, we have no hesitation in holding that consumption of electricity in excess of the sanctioned/connected load shall be an 'unauthorised use' of electricity in terms of Section 126 of the 2003 Act. This, we also say for the reason that overdrawal of electricity amounts to breach of the terms and conditions W.P.(C) No. 29073/2008 -:2:- of the contract and the statutory conditions, besides such overdrawal being prejudicial to the public at large, as it is likely to throw out of gear the entire supply system, undermining its efficiency, efficacy and even increasing voltage fluctuations. In somewhat similar circumstances, where the consumer had been found to be drawing electricity in excess of contracted load and the general conditions of supply of electricity energy by the Board and Clause 31(f) of the same empowered the Board to disconnect supply and even levy higher charges as per the tariff applicable, this Court held that such higher tariff charges could be recovered. While noticing the prejudice caused, the Court in the case Bhilari Rerollers and others v. M.P.Electricity Board and others (2003 KHC 1521 : 2003 (7) SCC 185 : JT 2003 (7) SC 215), held as under: “21. The respondent Board, therefore, is entitled to raise the demand under challenge since such right has been specifically provided for and is part of the conditions for supply and particularly when such drawal of extra load in excess of the contracted load is bound to throw out of gear the entire supply system undermining its efficiency, efficacy not only causing stress on the installations of the Board but considerably affect other consumers who will experience voltage fluctuations. Consequently, we see no merit in the challenge made on behalf of the appellants. The appeals, therefore, fail and shall stand dismissed but with no costs.”

3. In that view of the authoritative pronouncement of the Apex Court, I set aside the order of the assessing authority as well as the appellate authority and remit the matter to the assessing officer to dispose of the same in accordance with the judgment referred above. Learned counsel for the petitioner submits that no penalty can be levied under Section 126 of the W.P.(C) No. 29073/2008 -:3:- Electricity Act, 2003. The assessing authority, while considering the matter, shall take into consideration all the observations of the State Electricity Regulatory Commission in D.P.75/2009 dated 19.1.2010 and the judgment of the Apex Court and decide the question afresh after giving the petitioner an opportunity of being heard. The entire exercise shall be completed within a period of two months from the date of receipt of a copy of this judgment subject to the condition that, as agreed, the petitioner deposits 25% of the demand within one month. Amount, if any, paid or deposited shall be given credit to. In order to avoid delay, let the petitioner appear before the authority along with a copy of this judgment on 31.12.2012. It is open to the petitioner to raise all relevant points before the assessing authority, if so advised. Writ petition is disposed of as above. sd/- B.P. RAY, JUDGE. W.P.(C) No. 29073/2008 -:4:-

This is the original judgment text, reproduced from the public court record. Always verify it against the official record before relying on it in a filing — check it on Kerala High Court or eCourts case status. ← Search more judgments