✦ Calcutta High Court · 24 Feb 2026

INDUS TOWERS LTD. v. SHAHANUR ALAM

Case at a glance

Outcome

Allowed

adjudication by the learned Arbitrator, this application is allowed

Provisions considered

Key paragraphs

  • Para 1616. AP-COM 42 of 2026 is disposed of accordingly. pkd. (SHAMPA SARKAR, J.)

Judgment

the licensor. It is contended by Mr. Sen learned senior advocate that the agreement for Leave and License also contemplated that upon determination of the agreement, the licensor should allow the licensee to remove the equipments and thereafter the licensee shall deliver khas, vacant and peaceful possession of the said space to the licensor, subject to full refund of the security deposit and other admissible dues.

#6. It is contended that since May 24, 2007, the petitioner was in lawful possession of the subject property and was duly tendering the agreed monthly consideration towards discharge of its contractual obligations under the said agreement. The relationship between the parties began to sour due to arbitrary and exorbitant demand being made by the respondent over and above the agreed contractual consideration.

#7. The dispute arose due to petitioner refused to accept such unlawful claim which eventually led to the termination of license agreement upon invoking Clause 15.2 of the agreement.

#8. The leave and license agreement was terminated by letter dated 9th December, 2019 with effect from 30 days of receipt of such notice. The petitioner also 3 requested the respondent to provide safe passage to their personnel, so that the mobile tower could be dismantled and removed.

#9. When the petitioner sought to remove the apparatus, equipments, accessories etc. the respondent obstructed. Thus, an application for interim order was filed before this Court under Section 9 of the Arbitration and Conciliation Act,

#1996. First, an order was passed by this Court, permitting the petitioner to make an inventory. The application was then disposed of, permitting the petitioner to remove the articles. The petitioner invoked arbitration, claiming damages for the loss of business as the equipments, accessories etc. were lying idle and could not put to use although they were operational.

#10. A notice invoking arbitration was issued on March 21, 2025. The said notice was served in terms of clause 22 of the agreement, however the respondent avoided such service. The petitioner has a claim of more than Rs. 30 lakhs. Clause 24 of the Leave and License Agreement dated May 24, 2007 provides for resolution of disputes through arbitration. The clause is quoted below: “24. Arbitration:

24.1 The Parties hereto agree that any disputes, differences or controversies arising out of or in connection with these presents and/or in any way or in any manner touching and/or concerning the dealing and transaction between the parties herein as recorded in this Agreement shall be referred to and settled and/or adjudicated upon Arbitration by the sole Arbitrator to be appointed by the Chief Executive Officer/Chief Operating Officer of HESL, West Bengal and the Parties hereby consent to the same.

24.2 Such Arbitration proceeding or proceedings will be conducted in accordance with the Arbitration and Conciliation Act, 1996 and/or with the statutory modifications thereof and/or subsequent enactment thereof.

24.3 The venue of such arbitration proceeding or proceedings shall be at Kolkata.

24.4 The Arbitration shall be conducted in English Language only. 4

24.5 The award to be given by the sole Arbitrator shall be final in all respects and shall also binding upon both the parties.”

#11. The venue of arbitration has been agreed to be Kolkata.

#12. Under such circumstances, keeping all the issues between the parties open for adjudication by the learned Arbitrator, this application is allowed. The objections which may be available to the respondents may be raised before the learned Arbitrator. All questions on arbitrability, admissibility of the claim, limitation etc. shall be decided by the learned Arbitrator, if raised. The respondent may also raise a counter claim.

#13. This Court has not entered into the merits of the issues involved. The consideration of the application is limited to the existence of an arbitration clause and upon prima facie assessing that there are disputes between the parties.

#14. Under such circumstances, this Court refers the matter to arbitration by appointing Mr. Kaushik Chowdhury, Advocate, Bar Library Club 1st Floor, [Mobile No. 9830262599] as the sole arbitrator, to arbitrate upon the disputes. The learned Arbitrator shall comply with the provisions of Section 12 of the Arbitration and Conciliation Act, 1996.

#15. The learned Arbitrator shall be at liberty to fix her remuneration as per the schedule of Arbitration and Conciliation Act, 1996.

#16. AP-COM 42 of 2026 is disposed of accordingly. pkd. (SHAMPA SARKAR, J.)

Questions this judgment answers

What did the Court decide in this case?

The Court recorded the following disposition: adjudication by the learned Arbitrator, this application is allowed

Which statutory provisions did this judgment involve?

Arbitration and Conciliation Act, 1996 — ss. 9, 12.

Which court decided this case, and when?

Calcutta High Court, on 24 Feb 2026. The bench was SHAMPA SARKAR.

Precedent status how later indexed judgments have treated this case

No treatment data yet for this judgment in the Courts & Cases corpus.

Absence of data is not a statement about the judgment’s standing — the corpus covers only judgments we index and link with cited evidence.

Why is this linked?

This is the original judgment text, reproduced from the public court record. Always verify it against the official record before relying on it in a filing — check it on Calcutta High Court or eCourts case status (search case no. Com No. 42 of 2026). ← Search more judgments