✦ Calcutta High Court · 16 Mar 2026

Bridge and Roof Company (India) Ltd. & Anr. v. The Assistant Labour Commissioner (Central), Kolkata & Anr.

Case at a glance

Provisions considered

Key paragraphs

  • Para 1414. Accordingly, the impugned order dated 17th June, 2025 and a certificate dated 09.02.2026, be stayed till disposal of the appeal to be filed before the Appellate Authority.
  • Para 1616. WPA 6061 of 2026 stands disposed of.

Judgment

hereby disposed of.”

#5. It is the case of the petitioner that the said authority held the applicant/private respondent herein was to be treated to be in continuous service from 17.03.1980

28.02.2021 and granted gratuity accordingly.

#6. The petitioner submits the private respondent has been paid gratuity for the period from April 2006 to February 2021 when he was in continuous service.

#7. It is the case of the petitioner that from March 1980 to March 2006, the petitioner was not in uninterrupted service and, as such, he is not entitled to gratuity for the said period on the 3 basis of a certificate issued by an authority not empowered to do so and having been relied upon by the Controlling Authority.

#8. Learned counsel has placed a copy of the P.F. Contribution for the period from March 1995 to November 1995 as an example to show that the statement clearly shows that there is no contribution made in respect of the private respondent herein the period December 1995 to February 1996. In spite of the said records, the certificate has been issued stating applicant/private respondent was in continuous service.

#9. It further submitted there are documents filed which can be placed before the authority concerned to show that the petitioner is not entitled to pay the gratuity for the period from March 1980 to March 2006.

#10. Documents annexed substantiate the contention of the petitioner showing that the petitioner was engaged in different projects from time to time. After completion of certain payment in one project the petitioner after a gap or interruption was engaged in another project under the petitioner. It is thus submitted that the documents prima facie clearly shows that the private respondent was not in continuous service and there has 4 been no uninterrupted service rendered by the private respondent which entitles him gratuity for the said period.

#11. Learned counsel for the private respondent submits that the order is an appealable order but the petitioner having been preferred an appeal and it is only when the petitioner has been served with the certificate on 09.02.2026 that the petitioner has approached this Court. It further submitted the private respondent has been in continuous service since 1980 and that he has been put in different projects from time to time and there has been gap but it is under the same employer being the petitioner herein. As such, the private respondent has put in continuous service from March 1980 to March 2006 and is entitled to the said amount of which he is being deprived.

#12. On hearing the learned counsels for the parties and on perusal of the materials on record, it appears that the petitioner has placed certain documents which prima facie shows that the petitioner has an arguable case as to the continuous service having not been put in by the private respondent from March 1980 to March 2006. As such, the order is an appealable order and the petitioner was to prefer an appeal within the statutory period of 5 120 days. There is a delay of three months in preferring the appeal. But considering that the issue is addressed the delay is hereby condoned in the interest of justice.

#13. But considering that the issue needs to be addressed, the petitioner is granted liberty to prefer an appeal before the Appellate Authority, within 30 days from the date of this order on furnishing a bank guarantee in respect of the amount of gratuity in preferring the appeal considering that the petitioner herein being a Government Institution prays for such liberty.

#14. Accordingly, the impugned order dated 17th June, 2025 and a certificate dated 09.02.2026, be stayed till disposal of the appeal to be filed before the Appellate Authority.

#15. It is made clear that in case no appeal is preferred within the period granted by this Court, the order of stay stands automatically vacated and the authorities shall be at liberty to proceed in accordance with law.

#16. WPA 6061 of 2026 stands disposed of.

#17. Urgent Photostat certified copy of this order, if applied for, be given to the parties, upon usual undertakings. (Shampa Dutt (Paul), J.)

Questions this judgment answers

Which statutory provisions did this judgment involve?

Payment of Gratuity Act.

Which court decided this case, and when?

Calcutta High Court, on 16 Mar 2026.

Precedent status how later indexed judgments have treated this case

No treatment data yet for this judgment in the Courts & Cases corpus.

Absence of data is not a statement about the judgment’s standing — the corpus covers only judgments we index and link with cited evidence.

Why is this linked?

This is the original judgment text, reproduced from the public court record. Always verify it against the official record before relying on it in a filing — check it on Calcutta High Court or eCourts case status (search case no. No. 48/51 of 2022). ← Search more judgments