✦ Kerala High Court · 25 Jun 2009

C.G.GOVINDAN KARTHA v. THE GENERAL MANAGER S.RAILWAY

AR No. 28 of 2008THOTTATHIL B RADHAKRISHNAN4 min read

Case at a glance

Provisions considered

Judgment

THOTTATHIL B.RADHAKRISHNAN, J.-------------------------------------------A.R.No.28 OF 2008 ------------------------------------------- Dated this the 25th day of June, 2009

O R D E R1.This is a request made under Section 11(6) of the ArbitrationConciliation Act, 1996. The request is filed and registeredwith this Court on 8.7.2008.

2.

There is no dispute between the parties that there is anarbitration agreement between them as defined in Section 2(1)(b) of the Act. The arbitration clause classifies the contractson the basis of the value of the claims in relation to whicharbitration is sought for. If the claims are above Rs.10 lakhs, the agreement provides for an Arbitral Tribunal consisting ofa panel of three Gazetted Railway Officers, not below JA gradeor two Gazetted Railway Officials not below JA grade and aRailway Officer retired not below the rank of SAG officer asthe arbitrators. For that purpose, the Railways have to send apanel of more than three names of Gazetted Railway Officersof one or more departments of the Railways, which may also AR.28/08Page numbersinclude the name(s) of retired Railway Officer(s) empaneled towork as Railway Arbitrator, to the Contractor within 60 daysfrom the date when a written and valid demand for arbitrationis received by the General Manager. The Contractor will beasked to suggest to the General Manager up to two names outof the panel for appointment as Contractor's nominees within30 days from the date of dispatch of the request by the Railways. The General Manager has to appoint at least oneout of them as the Contractor's nominee and will alsosimultaneously appoint the balance number of arbitratorseither from the panel or from the Presiding Arbitrator fromamongst the three arbitrators so appointed. The GeneralManager shall complete this exercise of appointing the Arbitral Tribunal within 30 days from the receipt of the namesof Contractor's nominees.

3.

On 1.11.2007, the petitioner placed his claims before the General Manager. Though the opening clause in thearbitration agreement provides for the Railways to give its AR.28/08Page numbersreply to it and the entitlement of the Contractor to claim forappointments of arbitrator and for recourse to arbitration, either on being dissatisfied by the reply of the Railways or onthe failure of the Railways to answer, what was done followingthe raising of claims on 4.6.2008 was that the list of names offour officers of the Railways was forwarded to the Contractorfor him to select two of them. Following that, on 19.6.2008,the Contractor notified the names of Sri.C.Somasekaran and Sri.C.Nandakumar, two among those who were included in thelist given by the Railways on 4.6.2008. Thereafter, nothinghappened till the institution of this arbitration request on8.7.2008. After this request was registered with this Court on8.7.2008, the Railways appointed a three member ArbitralTribunal on 19.8.2008.

4.

With the aforesaid facts, the petitioner stands to say thatfollowing the judgment of the Apex Court in Datar SwitchGears Ltd. v. TATA Finance Ltd. [(2000) 8 SCC 151] and the Division Bench of this Court in Divisional Railway Manger v. AR.28/08Page numbersWest Cost Agencies [2005(2) KLT 734], the Railways did nothave the right to make any appointment of arbitrator on19.8.2008 after the registration of this arbitration request on8.7.2008 and any right to make appointment had ceased by theinstitution of this arbitration request. In West CostAgencies(supra), this Court specifically dealt with theprovisions in the General Conditions of contract of the Railways, particularly clause 64, which is the arbitrationagreement in the case in hand also. Following the enunciationof law in paragraphs 11 and 12 of that judgment and the ratioof Datar Switch Gears Ltd (supra), quoted and relied on bythis Court in West Cost Agencies, the submission of thepetitioner stands.

Under such circumstances, the appointmentpurported to have been made by the Railways on 2.4.2008 isno appointment and that exercise is one without authority in asmuch as the appointment was made after the power to do sohas ceased in terms of the law laid in Datar Switch GearsLtd . AR.28/08Page numbers5.With the aforesaid, the appointment procedure agreed upon bythe parties has failed and necessary measure in terms of Section 11(6) of the Act needs to be taken as the guideline forthe choice of the arbitrator being that provided in Sub section8 of Section 11. The appointment procedure in clause 64 ofthe General Conditions of contract of the Railways does notinsist appointment of any person with any specified specilisedqualification or expertise in the field of Engineering, Accounting etc. It only insists on the appointment of aGazetted Railway Officer of a particular rank. That issufficient guideline to hold that no expertise of any peculiarnature is required for the appointment.

The subject matter ofthe contract is the work of provision of road approach andcirculating area at Nemom and Parassala as part of conversioninto crossing station. I do not find any ground as to why aformer Judge of this Court is not to be appointed as anarbitrator. AR.28/08Page numbers6. For the aforesaid reasons, this arbitration request is allowedappointing Mr.Justice B.M.Thulasidas, former Judge of this Court as the arbitrator. THOTTATHIL B.RADHAKRISHNAN,Judge.kkb.30/6.

Questions this judgment answers

Which statutory provisions did this judgment involve?

ArbitrationConciliation Act, 1996 — s. 11(6).

Which court decided this case, and when?

Kerala High Court, on 25 Jun 2009. The bench was THOTTATHIL B RADHAKRISHNAN.

Precedent status how later indexed judgments have treated this case

No known negative treatment found in the Courts & Cases corpus.

This is a result about the indexed corpus, not a finding that the judgment remains good law. Coverage may be incomplete.

Why is this linked?

This is the original judgment text, reproduced from the public court record. Always verify it against the official record before relying on it in a filing — check it on Kerala High Court or eCourts case status (search case no. AR No. 28 of 2008). ← Search more judgments