✦ High Court of Jammu & Kashmir and Ladakh · 13 Feb 2025

Harish Gupta v. Union of India Through Secretary, Ministry of Defence, New Delhi

AT JAMMU ARB P No. 71 of 20244 min read

Case at a glance

Outcome

Disposed of

Accordingly, the present petition is disposed of by appointing Maj

Provisions considered

Key paragraphs

  • Para 1212. With the above observation and direction, the petition stands disposed of. ) (Tashi Rabstan) Chief Justice Jammu: 13.02.2025 Pawan Angotra Whether the order is speaking? : Yes/No Whether the order is reportable? : Yes/No Pawan Angotra 2025.02.13 14:53 I attest to the accuracy and…

Judgment

Through :- Mr. Vishal Sharma, DSGI Coram: HON’BLE THE CHIEF JUSTICE JUDGMENT ….Respondent(s)

1.

Heard Mr. Sumit Moza, learned counsel for the petitioner and Mr. Vishal Sharma, learned DSGI for the respondents at length and perused the record.

2.

The present petition has been filed by the petitioner seeking appointment of an independent Arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996 read with clause 23 of Special Conditions of Contract and clause 37 of General Conditions of Contract (IAFW-1815Z) in pursuance to tender no. CDR 35 TF/04/2021-22 to settle the disputes that has arisen between the parties.

3.

Brief facts, which lead to the filing of the present petition, are that the petitioner is the Proprietor of M/S Harish Gupta firm and vide Notice Inviting Tender (NIT) bearing CA No. CDR-35 BRTF/ /2021-22 bearing Tender No. CDR-35 TF/04/2021-2022 dated 08.02.2022, the Commander 35 Border Roads Task Force invited online bids on single stage two bid system for Supply and 2 Arb P No. 71/2024 Stacking of Stone Aggregate 13.20 MM, 11.20 MM, 6.70 MM and COARSE Sand at HMP Site KM 24.800 on Ramban-Gul Road for re-surfacing works on Ramban-Gul Road and Nashri Bye-Pass Road in 52 RCC Sector under 35 BRTF project Beacon and the cost of estimated works was fixed at Rs. 84.14 lacs; that as per Clause 7 of NIT it was provided that the work was required to be completed within 180 days from the date of handing over the site.

4.

It is averred that the petitioner’s bid was lowest and as a result was declared as L1 and the letter of acceptance regarding the said work was issued by Commander 35 BRTF in favour of the petitioner vide letter dated 09.04.2022. It is further averred that in terms of the communication dated 17.05.2022, the petitioner was directed to supply and stack the stone aggregate 13.20 MM, 11.20 MM, 6.70 MM and Coarse Sand at HMP Site as provided in the contract and the petitioner made available the same, however, despite repeated requests the site was not handed over to the petitioner for almost three months; that the respondents verbally directed the petitioner to make the supplies vehicle-wise in piece-meals as the respondents did not have a proper dumping yard and as per the consumption of the material in the plant, the petitioner could not dump material in a single go and the material was dumped every alternate day as per the requirement; that the respondents have issued the impugned cancellation letter dated 02.02.2023 for cancellation of contract and the ground taken in the said letter was that the material was not supplied by the petitioner since 24.12.2022, due to which the progress of the project had been stalled.

5.

It is further contended that aggrieved of the cancellation letter dated

02.02.2023 issued by the respondent No. 3, the petitioner invoked the jurisdiction of this Court under Section 9 of the Arbitration and Conciliation Act for seeking interim relief by way of filing Arb P No. 05/2023 and this Court vide order dated 3 Arb P No. 71/2024

27.02.2023 passed the interim direction, whereby the respondents have been restrained from invoking the risk and cost retendering option with respect to the contract work against the petitioner. It is further contended that vide letter dated

12.07.2023, the petitioner requested the respondents to refer all the claims to the Arbitrator at an earliest, however, the respondents are acting as mute spectator and have not referred the claims before the Arbitrator till date

6.

In the above backdrop, the petitioner approached this Court by preferring the present petition seeking appointment of an independent arbitrator under Section 11 of Arbitration and Conciliation Act, 1996 read with clause 23 of Special Conditions of Contract and clause 37 of General Conditions of Contract (IAFW-1815Z) in pursuance to tender no. CDR 35 TF/04/2021-22 to settle the disputes arising between the parties.

7.

Mr. Vishal Sharma, learned DSGI has resisted this petition by way of filing detailed objections and perusal of the same would show that a dispute exists between the parties.

8.

The fact that the petitioner has raised certain claims which, according to the petitioner, have not been addressed by the respondents, this Court is of the view that a dispute exists between the parties, which would require resolution in accordance with the aforementioned Clause 23 of Special Conditions of Contract and Clause 37 of General Conditions of Contract and this court is of the view that the dispute has to be ultimately decided by an Arbitrator.

Operative part

9.

Accordingly, the present petition is disposed of by appointing Maj. General K. Gajria (Retd.), 11-K/51, Lajpat Nagar-2, New Delhi-110 024 to act as the sole Arbitrator, who shall proceed in the matter to decide the dispute between the parties and make an award in accordance with law after hearing the 4 Arb P No. 71/2024 parties and charging the prescribed fee along with incidental expenses, as per applicable guidelines and rules, to be shared by the parties.

11.

Parties may raise their claims and counter claims before the Arbitrator. Registry to inform the learned Arbitrator accordingly.

12.

With the above observation and direction, the petition stands disposed of. ) (Tashi Rabstan) Chief Justice Jammu: 13.02.2025 Pawan Angotra Whether the order is speaking? : Yes/No Whether the order is reportable? : Yes/No Pawan Angotra 2025.02.13 14:53 I attest to the accuracy and integrity of this document

Questions this judgment answers

What did the Court decide in this case?

The Court recorded the following disposition: Accordingly, the present petition is disposed of by appointing Maj

Which statutory provisions did this judgment involve?

Arbitration and Conciliation Act, 1996 — ss. 9, 11.

Which court decided this case, and when?

High Court of Jammu & Kashmir and Ladakh, on 13 Feb 2025.

Precedent status how later indexed judgments have treated this case

No known negative treatment found in the Courts & Cases corpus.

This is a result about the indexed corpus, not a finding that the judgment remains good law. Coverage may be incomplete.

Why is this linked?

This is the original judgment text, reproduced from the public court record. Always verify it against the official record before relying on it in a filing — check it on High Court of Jammu & Kashmir and Ladakh or eCourts case status (search case no. AT JAMMU ARB P No. 71 of 2024). ← Search more judgments