✦ Madras High Court · 25 Feb 2003

M.P.Dhanaraj v. The Tamil Nadu Electricity Board

Writ Petition No. 17243 of 1997E PADMANABHAN18 min read

Case at a glance

Outcome

Quashed

proceedings of both the respondents are quashed

Provisions considered

Key paragraphs

  • Para 55. As seen from the Enquriy report, the enquiry Officer held that charges 1 and 2 were not proved and charges 3 and 4 were proved. The petitioner submitted an appeal on 26.5.1995 which was rejected. Again the petitioner submitted a memorial on 1.8.1996 which…

Judgment

For respondents :: Mr.V.Radhakrishnan :

O R D E R The petitioner, an Executive Engineer in the Tamil Nadu Electricity Board initially prayed for the issue of writ of certiorarified mandamus calling for the records of the 1st respondent in his proceedings (permanent) B.P. (Ch) No.178 dated 25.7.1995 and quash the same as illegal, and direct the respondents to accord all attendant benefits withheld in view of the punishment awarded in the above impugned order and pass such further or other orders.

2.

As an objection was raised by Mr.V. Radhakrishnan, learned counsel appearing for the respondent, the petitioner moved for amendment of the relief. The amendment was ordered by this court and the amended relief prayed for by the petitioner reads thus:- "The petitioner, prays for the issue of writ of certiorarified mandamus calling for the records of the 1st respondent in his proceedings (permanent) B.P. (Ch) No.178 dated 25.7.1995 and that of the appellate order namely, (Permanent) B.P. (F.B.) No.37/96-1, dated 31.5.1996 quash the same as illegal, and direct the respondents to accord all attendant benefits withheld in view of the punishment awarded in the above impugned order and pass such further or other orders. "

3.

As early as 24.11.1997, notice of motion was ordered by this court to the respondent and with the consent of counsel on either side, the writ petition is taken up for final disposal.

4.

The writ petitioner during 1978 desired to purchase a ready built house and submitted an application for sanction. The petitioner has also applied for sanction of house building advance which was registered and assigned priority. The petitioner's request for purchase was permitted on 30.3.1979 by the second respondent. The Executive Engineer (Civil) who inspected the building reported that the construction of the building is different from that of the approved plan and hence the petitioner decided to submit a revised plan. At that stage, the petitioner was selected for foreign assignment and deputed to Bhutan. The petitioner therefore could not pursue the matter by submitting a revised plan. The petitioner's wife chose to purchase the same house by selling her own jewels and taking a loan. The petitioner filed a return with respect to the property as on 31.12.1981 setting out the said particulars as well as the property which his wife has purchased. During 1987, the petitioner applied for permission to alienate a plot and construct a house. The application was kept pending for a considerable period. As there was no response, the petitioner's wife received advance from the buyer and purchased a plot at Coimbatore. The petitioner divided the plot into two and sold two portions to a different persons. The application for permission which was under process was delayed and no final order has been passed. Suddenly, the petitioner was served with a charge memo on 3.9.1994 by the Board alleging that the petitioner has violated the conduct regulations regarding acquisition and disposal of immovable property Without proper permission. Four charges were framed against the petitioner. The petitioner submitted a detailed explanation on 27.9.1994 denying the charges and opted for oral enquiry. The disciplinary authority appointed the Superintending Engineer Udumalpet Electricity Distribution Circle to be the Enquiry Officer and enquriy was conducted by the said authority. The Enquiry findings were not disclosed to the petitioner, nor it has been communicated till the penalty as imposd. However, final order has been passed by the first respondent on 25 .7.1995 imposing punishment of stoppage of increment for one year with cumulative effect. Along with the final order, the enquiry report was communicated.

5.

As seen from the Enquriy report, the enquiry Officer held that charges 1 and 2 were not proved and charges 3 and 4 were proved. The petitioner submitted an appeal on 26.5.1995 which was rejected. Again the petitioner submitted a memorial on 1.8.1996 which was also rejected. Being aggrieved by the said proceedings, the present writ petition has been filed.

6.

According to Mrs. Arulmozhi, learned counsel appearing for the petitioner, the proceedings are vitiated by illegality, suffer with error apparent on the face of the record, violative of principles of natural justice, violative of the Tamil Nadu Electricity Board Employees (Discipline and Appeal) Regulations, in that what is required by Regulation 8(a) proviso has not been followed, besides violation of other provisions of the Tamil Nadu Electricity Board Employees ( Discipline and Appeal) Regulations.

7.

On behalf of the respondents a counter has been filed by the Secretary to the TNEB. According to the respondent 4 charges were framed against the petitioner and he was called upon to state his explanation to the charges besides he was required to file the questionnaire duly filled. The petitioner submitted his explanation on 27.9.1994 and opted both for enquiry as well as a personal hearing. The Superintending Engineer, Udumalpet Electricity Distribution Circle was appointed as the Enquiry Officer, who conducted the oral enquiry on 13 .1.1995. The enquiry officer submitted his report holding charges 1 and 2 have not been proved, but charges 3 and 4 are substantiated. The first respondent by the Board's proceedings dated 25.7.1995 imposed the punishment of stoppage of increment for a period of one year with cumulative effect. The appeal preferred as against the said penalty has been dismissed by the Board on 31.5.1996. The memorial preferred under Regulation 24 was also rejected. It is contended that the petitioner has not challenged the appellate proceedings, but has challenged the original proceedings and therefore this writ petition is not maintainable.

8.

According to the respondents, the enquiry officer after conducting the enquiry and after affording opportunity to the petitioner submitted his report finding that the charges 1 and 2 have not been substantiated while charges 3 and 4 are proved. After considering the report, the first respondent imposed punishment of stoppage of increment for one year with cumulative effect, which is a minor punishment under Regulation 5 and therefore there is no necessity to communicate the enquiry report, nor it is required to communicate a copy of the report and afford opportunity to the petitioner. It is contended that having regard to the minor punishment imposed on the petitioner, it is not necessary to issue any further notice or opportunity or communicate the report submitted by enquiry officer. It is contended that proceedings has been conducted strictly in accordance with the Tamil Nadu Electricity Board Employees (Discipline and Appeal) Regulations and no interference is called for in this writ petition.

9.

It is also contended that the petitioner is guilty of conduct regulations and there are sufficient materials in this respect as has been set out in the enquiry officer's report. It is contended that no interference is called for with the impugned proceedings.

10.

In this writ petition the following points arise for consideration:- (A) Whether the impugned proceedings imposing the punishment of stoppage of increment for one year with cumulative effect is liable to be quashed as violative of principles of natural justice in that no opportunity has been afforded to the petitioner to put forth his objections with respect to the enquiry officer's report? (B) Whether the impugned proceedings are liable to be quashed for contravention of Regulation 5 and 8 of the Tamil Nadu Electricity Board Employees (Discipline and Appeal) Regulations? (C) Whether the writ petition is liable to be dismissed on the ground that the petitioner had not challenged the proceedings of the second respondent, the appellate authority? (D) To what relief, if any? 11. Mr.V.Radhakrishnan, learned counsel appearing for the respondents raised the preliminary objection that the writ petition is not maintainable, in that the proceedings of the appellate authority has not been challenged and after the disposal of the appeal, the proceedings of the original authority cannot be challenged as the proceedings of the original authority merges with the proceedings of the appellate authority. Though such a contention is hyper-technical but the learned counsel for the respondents relied upon the pronouncement of the Apex Court in 2000 (6) SCC 359 in this respect. However, the counsel for the petitioner moved for amendment of the relief and the amendment has been ordered. After the amendment, it is clear that the writ petitioner has not only challenged the proceedings of the disciplinary authority, the first respondent, but also the appellate authority. Therefore this contention will no longer survive. Hence this point is answered against the respondents.

12.

The other points could be considered together. The following facts are not in dispute: (i) Charges were framed under Regulation 8(b) of the Tamil Nadu Electricity Board Employees (Discipline and Appeal) Regulations; (ii) the petitioner submitted his objections and requested for oral enquiry and personal hearing; (iii) the disciplinary authority appointed an enquiry officer; (iv) the enquiry officer conducted an enquiry and submitted his report finding that the petitioner is guilty of two charges while exonerating him in respect of the remaining two charges; (v) the enquiry report has not been communicated to the petitioner prior to the imposition of punishment and it was communicated only along with the penalty proceedings; (vi) no opportunity was afforded to put forward the objections with respect to the findings recorded by the enquiry officer; (vii) the disciplinary authority agreed with the enquiry officer's report and imposed minor penalty without affording an opportunity of hearing.

13.

In the light of the above admitted facts, the two points have to be answered. There is no dispute that the first respondent is the disciplinary authority. Regulation 5 prescribes penalties that may be imposed on the employees of the Board for good and sufficient reasons. Penalty of censure, withholding of increments or promotion, recovery from pay and suspension are categorised as minor penalties while reduction to a lower rank, compulsory retirement, removal from service, dismissal from service are categorised as major penalties, which could be imposed on a Board employee. Regulation 8 prescribes the procedure for imposing penalties. For imposition of minor penalties the procedure is prescribed in Regulation 8(a) and the procedure being affording a reasonable opportunity of making representation and the same shall be taken into consideration before imposition of minor penalty. For imposition of major penalty, the procedure is prescribed in Regulation 8(b). Regulation 8(b) prescribes an elaborate procedure of framing of charges, affording opportunity calling upon the petitioner to state his explanation, appointment of enquiry officer, holding an enquiry, submission of enquiry report, affording opportunity to state objections and personal hearing and thereafter only a major penalty could be imposed.

14.

In the present case the penalty imposed being "withholding of the increment with cumulative effect", strictly speaking such penalty will not fall under Regulation 5(ii). It may fall under Regulation 5 (iii) which is categorised as a major penalty. However, this controversy need not be decided in the present case. Proviso to Regulation 8(a) mandates that to withhold increments of pay with cumulative effect for any period, sub clause/regulation (b) of Regulation 8 shall be followed. Proviso to sub clause/regulation (a) of regulation 8 reads thus:- "Provided further that, in every case where it is proposed, after considering the representation, if any, made by the employee to withhold increment(s) of pay and such withholding of increment(s) is likely to affect adversely the amount of pension payable to the employee or to withhold increment(s) of pay without cumulative effect fro a period exceeding three years or to withhold increment(s) of pay with cumulative effect for any period, the procedure laid down in sub regulation (b) shall be followed before making any order imposing on the employee any such penalty. "

15.

It is clear from the above Regulation that to withhold increments with cumulative effect for any period, the procedure prescribed for imposing major penalty in Regulation 8(b) has to be followed. Admittedly though charges were framed the petitioner was required to state his explanation, enquiry was conducted, enquiry report was submitted, but without affording an opportunity to state objections and without affording a personal hearing, which is the substantial part of the sub clause/regulation (b) of Regulation 8, the penalty of stoppage of increment with cumulative effect has been imposed in the present case. Therefore it is clear that sub clause/regulation (b) of Regulation 8 has not been followed. Mr.V.Radhakrishnan, learned counsel for the respondents has to necessarily admit that sub clause/ regulation (b) of Regulation 8 has not been followed before imposing punishment of stoppage of increment with cumulative effect.

16.

Regulation 8(b)(iii) prescribes that before making an order imposing such penalty, the disciplinary authority has to furnish the delinquent official, a copy of the report of the enquiry or personal hearing or both as the case may be and call upon the delinquent to submit his further representation if any and thereafter after consider the representation as well as evidence adduced during enquiry to impose punishment. In the present case admittedly the enquiry report has not been communicated to the writ petitioner before imposition of penalty, nor the petitioner has been afforded an opportunity to state his objection, nor the petitioner has been heard. Thus Regulation 8(b)(iii) has been violated in the imposition of impugned penalty.

17.

The learned counsel for the petitioner apart from the above two contentions contended that there is violation of principles of natural justice. In this case, the very Regulation itself namely 8(a) and (b) provides for communication of the copy of the enquiry report and for affording an opportunity to state objection as to the findings as well as a hearing. Apart from that it is the settled law that enquiry report should be communicated, objection should be called for and thereafter impose such penalty as the disciplinary authority may decide to impose. Mrs. Arulmozhi, learned counsel contended that the procedure adopted in this case is vio lative of principles of natural justice and on this short ground also the impugned proceedings are liable to be quashed. Per contra, Mr.V.Radhakrishnan, learned counsel appearing for the respondents contended that the punishment imposed being minor, no opportunity need be given. This contention advanced by Mr.V.Radhakrishnan cannot be sustained in the light of the proviso to Regulation 8(a) as well as 8(b)(iii). The above provisions which are mandatory have been violated by the respondents and this is fatal to the impugned proceedings.

Questions this judgment answers

What did the Court decide in this case?

The Court recorded the following disposition: proceedings of both the respondents are quashed

Which statutory provisions did this judgment involve?

Constitution of India — art. 226.

Which court decided this case, and when?

Madras High Court, on 25 Feb 2003. The bench was E PADMANABHAN.

Precedent status how later indexed judgments have treated this case

No known negative treatment found in the Courts & Cases corpus.

This is a result about the indexed corpus, not a finding that the judgment remains good law. Coverage may be incomplete.

Why is this linked?

This is the original judgment text, reproduced from the public court record. Always verify it against the official record before relying on it in a filing — check it on Madras High Court or eCourts case status (search case no. Writ Petition No. 17243 of 1997). ← Search more judgments