'l . V.K. Kartheek Chukkapalli v. The State of
Case Details
Petition under Article 226 of the Constitution of lndia praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased to issue writ order or direction more pa(icularly one in the nature of WRIT OF MANDAMUS declaring the action of the respondents in not processing the application of the Petitioner to provide for Domestic 3 Phase, total Domestic Load of 50000 watts vide Reg.No. NR915254312339 connection to the petitioner in respect of the Residential Building Plot No.2l1, in Survey No.25lp, admeasuring 167 sq. yards, situated at Phase-1, Kancha Gachibowli (V), Serilingampally (M), ra*ffi7 l' ,-.-- t' " dif . Under GHIVC, ft.sn,3a Reddy District, T.S., bounded by North. Plot No.2'12, South. Plot No.2'10, East. '18 Mtrs Wide Road, West. Plot No.190. Ancl not providing electricity connectic,n lo the above referred premises as illegal and zlrbitrary IA NO: '1 OF 2025 Petition underr Section 151 CPC praying that in the circumstilnces stated in the affidavit filed in s:pport of the petition, the High Court may be pleased to direct the respondents 2 to 7 to process the application pf the petitioner to provide Domestic 3 Phas;e, total Domestic Load of 50000 watts vide Reg.No. NR915254312339 connection to the petitioner in respect of the Residential Building Plot No.211, in Survey No.2SlP, admeasuring '167 sq. ya'ds, situated at Phase-'1 , Kancha C,achibowli (V), Serilingampally (M), Under (3HMC, Ranga Reddy District, T.S , bounded by North. PIot No.212; South. Plot No.210; East. 18 lvltrs Wide Road: West. Plot No.'190. Counsel for the Petitioners: SRl. THAKUR ROOPA SINGH Counsel for the Respondent No.1: GP FOR ENERGY Counsel for the Respondent Nos.2 to 7: SRI N. SREEDHAR REDDY SC FOR TSSPDCL The Court made the following: ORDER THE HON'BLE SRI JUSTICE PULLA I{ARTHTK WRIT PETITION No,7924 OF 20125 ORDER: With the consent of both the parties, this Writ Petition is taken up for disposal, at the admission stage itself.
2. This Writ Petition is filed, under Article 226 of ttre Constitution of India, seeking the following relief ".. .to issue u.tit order or direction more parTicularlg one in the nohtre of Wnt of Mandamus declaing the action of the respondents in not processing th.e application of the petitioner to prouide for Domestic 3 Phase, - total Domestic Load of 5OO0O u)otts uide Reg. No.NR915254312339 connection to the petitioner in respect of tlrc Residential &itding Plot No.211, in Surueg No.25/P, admeasuring 167 sq. yards, situated at Phase-l, Kqncha Gachibotuli (V), Serilingampallg (M), under GHMC, Ranga Reddg Distict,7.5., bounded bA North: ptot No.212; South: Plot No.210; East:l8 Mtrs Wide Road; West: plot No.190. And not prouiding electricitg connection to the aboue referred premises as illegal and arbitrary and pass..."
3. Heard Smt.Thakur Roopa Singh, learned counsel for the petitioners; learned Government Pieader for Energz for respondent No.1; Sri N.Sreedhar Reddy, learned Standing Counsel for Telangana State Southern Power Distribution Company Limited, for respondent Nos.2 to Z; and Sri G.Madhusudhal Reddy, learned Stalding Counsel for Greater Hyderabad Municipal Corporation, for respondent No.8. u 2 :.,*rdlt PK,J \\p '1921 2025
4. Learnerl counsel for the petitioners submits that the subject ma,:ter of this Writ Petition is squarely covered by the order of this Court in W.P.No.242O5 of 2024, dated Og.O9.2024, and requested this Court to pass similar order in the present Writ Petition also. The same is not seriously disputed try the learned Government Pleader as well as learned Standing Counsel for the respondents. In viev,, of the above submissions and for the reasons
5. alike in 1.he order of this Court in W'P.No.242O5 of 2024, dated 09.09 .2024, tl:ris Writ Petition is disposed o: directing the resporLdents to consider the application, dated 10.03.2025t, submitted by the petitioners, for providing Domestic l] Phase, total Domestic Load of 50000 watts uide Reg. No. NlR'9 15254312339 connection to the petitioners in respect of t.he Residential Building Plot N o.2 I 1 , in Survey No.25/P, acimeasuring 167 sq. yards, situated a: Phase-l, Kancha Gachibowli (V), Serilingampaliy (M), under GHMC, Ranga Reddy District, Telangana, and pass appropriate orders, in accordance with law, as expeditiously as possible, preferably v;ithin a period of two (2) weeks from the date of receipt of zr copy of this order, subject to the petitioners --- --,.-t _*-_ E, l i 3 PK,J wp_7924 2025 making necessary payment, AS stipulated under the Electricity Act, 2003. Miscellaleous petitions pending, if aly, shall star-rd closed. There shall be no order as to costs. //TRUE COPY// ASSISTANT REGI SD/-A.V.S.PR SAD RAR SECTION OFFICER
1. The Principal Secretary Power and Energy Department Secretariat, Hyderabad-500022. 2 \,
8. The Chairman-cum-[Vanaging Director Telangana State Southem Power Distribution Company Limited., Vidyuth Soudha, Somajiguda, Hyderabad. Chief General [\,4anager commercial, [\rlint Compound TGSPDCL, Hyderabad. The Superintending Engineer, Telangana State Southern Power Distribution Company Limited, Vidyuth Soudha, Somajiguda, Hyderabad. The Divisional Engineer, Operation Gachibowli, TGSPDCL The Assistant Divisional Engineer, Operation Gachibowli, TGSPDCL The Assistant Engineer, Operation Gachibowli, TGSPDCL One CC to SRl. THAKUR ROOPA SINGH Advocate [OPUC]
9. '10 11 One CC to SRI N. SREEDHAR REDDY SC FOR TSSPDCL [OPUC] Two CCs to GP FOR ENERGY ,High Court for the State of Telangana. [OUT] Two CD Copies To,
8.... KKS GJP HIGH COURT DATED:1710312025 CC TODAY $' : ORDER WP.No.7924 ot 2025 1 s SrAIE o 7 o ..rt t C .J ?1 ll\[$ ?[15 -t .ruy]l':2 DISPOSING OF THE WRIT PETITION WITHOUT COSTS 6 A\ I i I I I I