Mr. Abhinav Sharma and Mr. Shreesh Pathak, Advs v. NEW DELHI MUNICIPAL COUNCIL
Case Details
Acts & Sections
Cited in this judgment
Through: Mr. Akshay Verma, Addl. Standing CORAM: HON'BLE MR. JUSTICE PURUSHAINDRA KUMAR KAURAV Counsel for NDMC. JUDGEMENT PURUSHAINDRA KUMAR KAURAV, J. (ORAL)
1. 2. Heard learned counsel for the parties. The present petition has been filed under Section 11 of the Arbitration and Conciliation Act, 1996 (the 1996 Act) by the petitioner, seeking appointment of an Arbitrator, to adjudicate upon the disputes that have arisen between the parties under the Agreement dated 12.02.2019. 3. The facts of the case would indicate that the petitioner was awarded the work by the by the respondent under the RIP Division during 2018-19 with sub-head as Operation and Maintenance of 35 nos. toilets blocks in NDMC area for the period of one year. 4. As per the case set up by the petitioner, the aforesaid work was Signature Not Verified Signed By:AMIT KUMAR SHARMA Signing Date:05.08.2025 18:34:57 Signature Not Verified Signed By:PURUSHAINDRA KUMAR KAURAV completed on 27.03.2017 to the full satisfaction of the respondent. Learned counsel for the plaintiff submits that the dispute has arisen in relation to the final bill including on account of clause 10C, which relates to refund of security deposit along with labour charge refund and alleged wrongful deduction of recovery etc. along with interest and cost of the arbitration. 5. The petitioner then contends that the respondent was approached for amicable resolution of the dispute through Dispute Resolution Committee (DRC). However, there was no satisfactory response from the respondent. 6. It is further submitted that the petitioner thereafter, by way of letter dated 11.12.2025, invoked Clause 25 of the agreement seeking reference of the dispute for arbitration. 7. Learned counsel for the petitioner further contends that the petitioner is entitle for a sum of Rs. 44,95,642/- as on the date of notice dated
11.12.2024. However, it is also submitted that to the extent of Rs. 7,98,412/- the claim stands admitted by the respondent. 8. The aforesaid contentions are vehemently refuted by learned counsel who appears for the respondent, who contends that the petitioner is not entitled for any amount. He further submits that even the final revised bill has not been submitted. 9. Though the aforesaid contention is again refuted by learned counsel who appears for the petitioner. 10. The Court takes note of the Clause 25 of the agreement dated
12.02.2019, which is extracted as under: “CLAUSE 25 Settlement of Disputes & Arbitration Except where otherwise provided in the contract, all questions and disputes relating to the meaning of the specifications, design, drawings Signature Not Verified Signed By:AMIT KUMAR SHARMA Signing Date:05.08.2025 18:34:57 Signature Not Verified Signed By:PURUSHAINDRA KUMAR KAURAV and instructions here-in before mentioned and as to the quality of workmanship or materials used on the work or as to any other question, claim, right, matter or thing whatsoever in anyway arising out of or relating to the contract, designs drawings, specifications, estimates, instructions, orders or these conditions or otherwise concerning the works or the execution or failure to execute the same whether arising during the progress of the work or after the cancellation, termination, completion or abandonment thereof shall be dealt with as mentioned hereinafter: (i) If the contractor considers any work demanded of him to be outside the requirements of the contract, or disputes any drawings, record or decision given in writing by the Engineer-in-Charge or if the Engineer in Charge considers any act or decision of the contractor on any matter in connection with or arising out of the contract or carrying out of the work, to be unacceptable and is disputed, such party shall (promptly within 15 days of the arising of the disputes request the Chief Engineer or where there is no Chief Engineer, the Additional Director General (CE/ADG) who shall refer the disputes to Dispute Redressal Committee (DRC) within 15 days along with a list of disputes with amounts claimed if any in respect of each such dispute. The Dispute Redressal Committee (DRC) shall give the opposing party two weeks for a written response, and, give its decision within a period of 60 days extendable by 30 days by consent of both the parties from the receipt of reference from CE/ADG. The constitution of Dispute Redressal Committee (DRC) shall be as indicated in Schedule „F‟. Provided that no party shall be represented before the Dispute Redressal Committee by an advocate/legal counsel etc. lf the Dispute Redressal Committee (DRC) fails to give its decision within the aforesaid period or any party is dissatisfied with the decision of Dispute Redressal Committee (DRC) or expiry of time limit given above; then either party may within a period of 30 days from the receipt of the decision of Dispute Redressal Committee (DRC), give notice to the Chief Engineer, CPWD, in charge of the work or if there be no Chief Engineer, the Additional Director General of the concerned region of CPWD or if there be no Additional Director General, the Director General, CPWD for appointment of arbitrator on prescribed (CE/ADG/DG) proforma as per Appendix XV under Intimation to the other party. Provided that no party shall be represented before DRC by an advocate/ legal counsel etc The CE/ADG/DG shall in such case appoint the sole arbitrator or one of the three arbitrators as the case may be within 30 days of receipt of such a request and refer such disputes to arbitration. Signature Not Verified Signed By:AMIT KUMAR SHARMA Signing Date:05.08.2025 18:34:57 Signature Not Verified Signed By:PURUSHAINDRA KUMAR KAURAV (ii) Wherever the Arbitral Tribunal consists of three Arbitrators the contractor shall appoint one arbitrator within 30 days of making request for arbitration or of receipt of request by Engineer-in- charge to CFJADG/DG for appointment of arbitrator, as the case may be, and two appointed arbitrators shall appoint the third arbitrator who shall act as the Presiding Arbitrator. In the event of
1. a. A party fails to appoint the second Arbitrator, or b. The two appointed Arbitrators fail to appoint the
2. Presiding Arbitrator, then The chairperson NDMC shall appoint the second or Presiding Arbitrator as the case may be. Disputes or difference shall be referred for adjudication through arbitration by a Tribunal having sole arbitrator where Tendered amount is Rs. 100 Crore or less. Where Tendered Value is more than Rs, 100 Crore, Tribunal shall consist of three Arbitrators as above. The requirements of the Arbitration and Conciliation Act, 1996 (26 of 1996) and any further statutory modifications or re- enactment thereof and the rules made there under and for the time being in force shall be applicable. It is a term of this contract that the party invoking arbitration shall give a list of disputes with amounts claimed, if any, in respect of each such dispute along with the notice for appointment of arbitrator and giving reference to the decision of the DRC. It is also a term of this contract that any member of the Arbitration Tribunal shall be a Graduate Engineer with experience in handling public works engineering contracts at a level not lower than Chief Engineer (Joint Secretary level of Government of India). This shall be treated as a mandatory qualification to be appointed as arbitrator. Parties, before or at the time of appointment of Arbitral Tribunal may agree in writing for fast track arbitration as per the Arbitration and Conciliation Act, 1996 (26 of 1996) as amended in 2015. Subject to provision in the Arbitration and Conciliation Act, 1996 (26 of 1996) as amended in 2015 whereby the counter claims if any can be directly filed before the arbitrator without any requirement of reference by the appointing authority, the arbitrator shall adjudicate on only such disputes as are referred to him by the appointing authority and give separate award against each dispute and claim referred to him and in all cases where the total amount of the claims by any party exceeds Rs. 1,00,.000/-, the arbitrator Signature Not Verified Signed By:AMIT KUMAR SHARMA Signing Date:05.08.2025 18:34:57 Signature Not Verified Signed By:PURUSHAINDRA KUMAR KAURAV shall give reasons for the award. It is also a term of the contract that if any fees are payable to the arbitrator, these shall be paid as per the Act The place of arbitration shall be as mentioned in Schedule F. In case there is no mention of place of arbitration, the arbitral tribunal shall determine the place of arbitration. The venue of the arbitration shall be such place as may be fixed by the Arbitral Tribunal in consultation with both the parties. Failing any such agreement, then the Arbitral Tribunal shall decide !he venue.”
11. The law with respect to the scope and standard of judicial scrutiny under Section 11(6) of the 1996 Act has been fairly well settled. This Court as well in the order dated 24.04.2025 in case of ARB.P. 145/2025 titled as Pradhaan Air Express Pvt Ltd v. Air Works India Engineering Pvt Ltd has extensively dealt with the scope of interference at the stage of Section 11. The Court held as under:- “9. The law with respect to the scope and standard of judicial scrutiny under Section 11(6) of the 1996 Act has been fairly well settled. The Supreme Court in the case of SBI General Insurance Co. Ltd. v. Krish Spinning1, while considering all earlier pronouncements including the Constitutional Bench decision of seven judges in the case of Interplay between Arbitration Agreements under the Arbitration & Conciliation Act, 1996 & the Indian Stamp Act, 1899, In re 2 has held that scope of inquiry at the stage of appointment of an Arbitrator is limited to the extent of prima facie existence of the arbitration agreement and nothing else.
10. It has unequivocally been held in paragraph no.114 in the case of SBI General Insurance Co. Ltd that observations made in Vidya Drolia v. Durga Trading Corpn.3, and adopted in NTPC Ltd. v. SPML Infra Ltd.,4 that the jurisdiction of the referral court when dealing with the issue of “accord and satisfaction” under Section 11 extends to weeding out ex-facie non-arbitrable and frivolous disputes would not apply after