✦ High Court of India · 28 Apr 2025

Mr. K.C. Tripathi, Advocate v. UNION OF INDIA ORS

Case Details High Court of India · 28 Apr 2025

Through: Ms. Aakanksha Kaul, Mr.Aman Sahani and Ms.Ashima Chopra, Advocates. HON'BLE MR. JUSTICE PURUSHAINDRA KUMAR KAURAV JUDGEMENT PURUSHAINDRA KUMAR KAURAV, J. (ORAL)

1. The present petition has been filed under Section 11(6) of the Arbitration and Conciliation Act, 1996 (the 1996 Act) by the petitioner, seeking appointment of an Arbitrator, to adjudicate upon the disputes that have arisen between the parties under the Terms of Arbitration Clause 70 of General Terms and Conditions of Contract I.A.F.W-2249. Signature Not Verified Signed By:PRIYA Signing Date:08.05.2025 12:26:22 1 Signature Not Verified Signed By:PURUSHAINDRA KUMAR KAURAV

2. Learned counsel for the petitioner submits that the petitioner is a registered contractor, and has been engaged by the respondents on multiple occasions for the execution of various civil and construction works. He submits that the Respondent No.1 is the Union of India through the Engineer-in-Chief (E-in-C), Military Engineer Services (MES), which is the authority responsible for the execution of infrastructure works for the Indian Army. Respondents Nos. 2 to 4 are subordinate offices functioning under Respondent No.1, and are responsible for administration and execution of works under the supervision and control of Respondent No.1, including for the appointment of an Arbitrator under the 1996 Act.

3. Learned counsel submits that the tender of the petitioner was accepted by the respondents, and a formal agreement was executed between the parties on 26.02.2021 for a total contract value of Rs. 39,45,380/-. The petitioner, vide letter dated 14.04.2021, requested the respondents to provide necessary drawings to enable the commencement of work, and simultaneously sought an extension of time owing to the lockdown imposed in Delhi from 06.04.2021 to 30.04.2021 due to the second wave of COVID-

19. However, despite repeated representations, the respondents failed to hand over the site or provide the requisite drawings and design mix, thereby committing a breach of the terms and conditions of the contract.

4. It is further submitted that vide letter dated 12.04.2021, the respondent issued a communication threatening cancellation of the contract, even though impediments to commencement of work were entirely attributable to their inaction. Thereafter, vide letter dated 08.06.2021, the Signature Not Verified Signed By:PRIYA Signing Date:08.05.2025 12:26:22 2 Signature Not Verified Signed By:PURUSHAINDRA KUMAR KAURAV petitioner reiterated the request for issuance of drawing, design mix (M-25), and approval of samples, noting the further complications arising due to lockdown restrictions and reverse migration of labour. Despite these representations, no remedial steps were taken by the respondents.

5. The petitioner further states that the work order dated 26.02.2021 could not be executed due to failure on part of the respondents in handing over the site, granting sample approvals, providing storage space for labour, and issuing drawings. It is also alleged that the drawings which were eventually furnished were defective, and the subordinate offices of the respondent were aware of this defectiveness and hence withheld the same. The contract itself, being a repair contract, had certain anomalies, such as the inclusion of a disproportionately large quantity of steel in the BOQ, which rendered execution unfeasible.

6. In light of the above, the petitioner, issued a notice under Condition 71 of the General Conditions of Contract (IAFW-2249) seeking amicable resolution of the dispute and raised the following claims:- (i) Risk and cost claim in the event of contract cancellation – Rs. 3,90,000/- (ii) Performance security amount – Rs. 1,19,000/- (iii) Loss of profits – Rs. 10,00,000/- (iv) Interest at the rate of 12% on the withheld amount (v) Litigation expenses – Rs. 1,50,000/-

7. It is submitted that despite service of notice under Condition 71, the respondents failed to respond or initiate amicable resolution. Consequently, the petitioner issued a further notice under Condition 70 of IAFW-2249 Signature Not Verified Signed By:PRIYA Signing Date:08.05.2025 12:26:22 3 Signature Not Verified Signed By:PURUSHAINDRA KUMAR KAURAV seeking appointment of a Sole Arbitrator within the prescribed period of 30 days. However, no arbitrator was appointed. Accordingly, learned counsel submits that the respondents have, by their inaction, forfeited their right to appoint an arbitrator. He submits that the total value of the claims raised is approximately Rs. 15,00,000/-.

9. Heard learned counsel appearing on behalf of the petitioner. The Court takes note of the Clause 70 General Terms and Conditions of Contract I.A.F.W-2249, which reads as under:- “70. Arbitration.- All disputes, between the parties to the Contract(other than those for which the decision of the C.W.E. or any other person is by the Contract expressed to be final and binding) shall, after written notice by either party to the Contract to the other of them, be referred to the sole arbitration of an Engineer officer to be appointed by the authority mentioned in the tender documents. Unless both parties agree in writing such reference shall not take place until after the completion or alleged completion of the Work or termination or determination of the Contract under Condition Nos. 55, 56 and 57 hereof. Provided that in the event of abandonment of the Works or cancellation of the Contract under Condition Nos. 52, 53 or 54 hereof, such reference shall not take place until alternative arrangements have been finalized by the Government to get the Works completed by or through any other Contractor or Contractors or Agency or Agencies. Provided always commencement or continuance of any arbitration proceeding hereunder or otherwise shall not in any manner militate against the Government’s right of recovery from the contractor as provided in Condition 67 hereof. If the Arbitrator so appointed resigns his appointment or vacates his office or is unable or unwilling to act due to any reason whatsoever, the authority appointing him may appoint a new Arbitrator to act in his place. The Arbitrator shall be deemed to have entered on the reference on the date he issues notice to both the parties, asking them to submit to him their statement of the case and pleadings in defence. The Arbitrator may proceed with the arbitration, exparte, if either party, inspite of a notice from the Arbitrator fails to take part in the proceedings. The Arbitrator may, from time to time with the consent of the parties, enlarge, the time upto but not exceeding one year from the date of his entering on Signature Not Verified Signed By:PRIYA Signing Date:08.05.2025 12:26:22 4 Signature Not Verified Signed By:PURUSHAINDRA KUMAR KAURAV the reference, for making and publishing the award. The Arbitrator shall give his award within a period of six months from the date of his entering on the reference or within the extended time as the case may be on all matters referred to him and shall indicate his findings, along with sums awarded, separately on each individual item of dispute. The venue of Arbitration shall be such place or places as may be fixed by the Arbitrator in his sole discretion. The award of the Arbitrator shall be final and binding on both parties to the Contract.”

10. The law with respect to the scope and standard of judicial scrutiny under Section 11(6) of the 1996 Act has been fairly well settled. This Court as well in the order dated 24.04.2025 in case of ARB.P. 145/2025 titled as Pradhaan Air Express Pvt Ltd v. Air Works India Engineering Pvt Ltd has extensively dealt with the scope of interference at the stage of Section 11. The Court held as under:- “9. The law with respect to the scope and standard of judicial scrutiny under Section 11(6) of the 1996 Act has been fairly well settled. The Supreme Court in the case of SBI General Insurance Co. Ltd. v. Krish Spinning,1 while considering all earlier pronouncements including the Constitutional Bench decision of seven judges in the case of Interplay between Arbitration Agreements under the Arbitration & Conciliation Act, 1996 & the Indian Stamp Act, 1899, In re 2 has held that scope of inquiry at the stage of appointment of an Arbitrator is limited to the extent of prima facie existence of the arbitration agreement and nothing else.

10. It has unequivocally been held in paragraph no.114 in the case of SBI General Insurance Co. Ltd that observations made in Vidya Drolia v. Durga Trading Corpn.,3 and adopted in NTPC Ltd. v. SPML Infra Ltd.,4 that the jurisdiction of the referral court when dealing with the issue of “accord and satisfaction” under Section 11 extends to weeding out ex-facie non-arbitrable and frivolous disputes would not apply after the decision of Re: Interplay. The abovenoted paragraph no.114 in the case of SBI General Insurance Co. Ltd reads as under:-

This is the original judgment text as indexed from the source corpus. Always verify against the official court record before relying on it in a filing — you can do so on eCourts or the Supreme Court of India website. ← Search more judgments