Brij Kishore Prasad Yadav & Ors. v. The State Of Bihar through Chief Secretary, State of Bihar, Patna

CIVIL WRIT JURISDICTION CASE No. 8069 of 2017RAJIV ROY3 min read

Case at a glance

Bench
RAJIV ROY

Provisions considered

Judgment

8.

Ram Tapesh Yadav, S/o Late Daroga Rai. All are Resident of Village and P.O.- Laxmipur, P.S. Moffasil Motihari, District- East Champaran. Versus ... ... Petitioner/s The State Of Bihar through Chief Secretary, State of Bihar, Patna Principal Secretary, Revenue and Land Reforms Department, State of Bihar, Patna. Principal Secretary, Water Resources Department, State of Bihar, Patna. Chief Engineer, Gandak Project, Water Resources Department, State of Bihar, Patna. Superintending Engineer, Gandak Project, Water Resources Department, State of Bihar, Patna. Executive Engineer, Gandak Project, Water Resources Department, State of Bihar, Muzaffarpur. Special land Acquisition Officer, Gandak Project, Water Resources Department, State of Bihar, Muzaf The Collector, East Champaran at Motihari.

9.

Addl. Collector, East Champaran at Motihari.

10.

District Land Acquisition Officer, East Champaran at Motihari.

11.

Circle officer, Sadar Motihari, East Champaran. ... ... Respondent/s

====================================================== Appearance : For the Petitioner/s For the Respondent/s ====================================================== CORAM: HONOURABLE MR. JUSTICE RAJIV ROY Mr. Rakesh Kumar No.1, Advocate Mr. Raj Kishore Roy, GP-18 : : 2 06-05-2024 Heard the parties. ORAL ORDER

2.

The present writ petition has been preferred for the grant of following relief/s:- Patna High Court CWJC No.8069 of 2017(2) dt.06-05-2024

(i) Issuance of an appropriate writ, order or direction commanding the respondents to forthwith make payment of compensation amount to the petitioners in accordance with law in respect of the land acquired; (ii) Issuance of an appropriate writ, order or direction commanding the respondents to forthwith implement and act in terms of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (for short 'the New Act') as the proceeding initiated under the Land Acquisition Act, 1894 (for short "The Old Act') have lapsed; (iii) Issuance of an appropriate writ, order or direction holding that there is no sovereign immunity to the respondents to misuse and abuse of power and to determine the reasonable amount of compensation to the petitioner; (iv) Issuance of an appropriate writ, order direction commanding the respondents not to exceed the area of the acquired land on the un-acquired exclusive land of the petitioner without the authority of law and ensuring its full protection with complete demarcation on the spot; (v) Any other relief of reliefs may be granted to the petitioner as he is found Patna High Court CWJC No.8069 of 2017(2) dt.06-05-2024 entitled to in the facts and circumstances of the case for the ends of justice.

3.

A counter-affidavit has been filed on behalf of the respondent No. 7 and paragraph 9 to 11 read as follows:- “(9) That it is stated that in the meantime, the Engineer-in-Chief, flood Control and Drainage, Water Resources Department, Bihar, Patna directed Engineer, Flood the Chief control and Drainage, Muzaffarpur vide letter no. 1640 dated-

14.11.2016 to inform the Special Land Acquisition Project, Officer, Muzafarpur Gandak that construction of pilot channel for flood protection work is a temporary measure and for this permanent acquisition of the land is not required. (10) That it is stated that in the light of the aforesaid decision, the Director, Land acquisition and Rehabilitation, Resources Department, Water Bihar, Patna directed the special Land Acquisition Officer, Gandak project, Muzaffarpur vide letter no. 2013 dated 9.12.2016 to take necessary steps in accordance with law. (11) That it is stated that pursuant to the aforesaid directions, the aforesaid land acquisition proceeding has been stopped and the land of the petitioners or any other raiyat has not been acquired. Hence no question of Patna High Court CWJC No.8069 of 2017(2) dt.06-05-2024 payment of compensation to anyone arise.”

4.

Copy of the counter-affidavit was served upon the learned counsel for the petitioner on 06.11.2017 and there is no rejoinder to it.

5.

From the aforesaid fact, it is clear that no acquisition process took place and on frivolous issue, the writ petition has been filed.

6.

Accordingly, the present writ petition stands

Precedent status how later indexed judgments have treated this case

No known negative treatment found in the Courts & Cases corpus.

This is a result about the indexed corpus, not a finding that the judgment remains good law. Coverage may be incomplete.

Why is this linked?

This is the original judgment text, reproduced from the public court record. Always verify it against the official record before relying on it in a filing — check it on Patna High Court or eCourts case status (search case no. CIVIL WRIT JURISDICTION CASE No. 8069 of 2017). ← Search more judgments