Judgment · Supreme Court
Case at a glance
Outcome
Allowed
The appeal is allowed in the aforesaid terms
Provisions considered
- Arbitration and Conciliation Act, 1996 ss. 9, 18, 34, 34(2)(a)(iii)
- Constitution of India art. 142
- Foreign Awards (Recognition and Enforcement) Act, 1961 s. 7(1)(b)(ii)
- Amendment Act, 2015
- Arbitration and Conciliation (Amendment) Act, 2015
- Applicability of the Arbitration and Conciliation (Amendment) Act, 2015
Judgment
verbatim reproduction of Article 24(3) of the UNCITRAL Model Law on International Commercial Arbitration. Similarly, Section 26(1) and (2) is a verbatim reproduction of Article 26 of the UNCITRAL Model Law. Sub-section (3) of Section 26 has been added by the Indian Parliament in enacting the 1996 Act. Sections 18, 24(3), and 26 are important pointers to what is contained in the ground of challenge mentioned in Section 34(2)(a)(iii). Under Section 18, each party is to be given a full opportunity to present its case. Under Section 24(3), all statements, documents, or other information supplied by one party to the arbitral tribunal shall be communicated to the other party, and any expert report or document on which the arbitral tribunal relies in making its decision shall be communicated to the parties. Section 26 is an important pointer to the fact that when an expert’s report is relied upon by an arbitral tribunal, the said report, and all documents, goods, or other property in the possession of the expert, with which he was provided in order to prepare his report, must first be made available to any party who requests for these things. Secondly, once the report is arrived at, if requested, parties have to be given an opportunity to put questions to him and to present their own expert witnesses in order to testify on the points at issue. [Paras 34-36] [575-D-E; 576-E-H; 577-A]
1.6 Under the rubric of a party being otherwise unable to present its case, the standard textbooks on the subject have stated that where materials are taken behind the back of the parties by the Tribunal, on which the parties have had no opportunity to comment, the ground under Section 34(2)(a)(iii) would be made out. [Para 37] [577-B] The Ground of Challenge under Section 34(2)(a)(iv)
1.7 So far as this defence is concerned, standard textbooks on the subject have held that the expression “submission to arbitration” either refers to the arbitration agreement itself, or to disputes submitted to arbitration, and that so long as disputes raised are within the ken of the arbitration agreement or the disputes submitted to arbitration, they cannot be said to be disputes which are either not contemplated by or which fall outside the arbitration agreement. The expression “submission to A B C D E F G H SSANGYONG ENG. & CONST. CO. LTD. v. NATIONAL HIGHWAYS AUTH. OF INDIA (NHAI) 531 arbitration” occurs in various provisions of the 1996 Act. Thus, under Section 28(1)(a), an arbitral tribunal “… shall decide the dispute submitted to arbitration …”. Section 43(3) of the 1996 Act refers to “… an arbitration agreement to submit future disputes to arbitration ….”. Also, it has been stated that where matters, though not strictly in issue, are connected with matters in issue, they would not readily be held to be matters that could be considered to be outside or beyond the scope of submission to arbitration. [Para 39] [581-E-H]
1.8 Where an arbitral tribunal has rendered an award which decides matters either beyond the scope of the arbitration agreement or beyond the disputes referred to the arbitral tribunal, as understood in Praveen Enterprises, the arbitral award could be said to have dealt with decisions on matters beyond the scope of submission to arbitration. In the guise of misinterpretation of the contract, and consequent “errors of jurisdiction”, it is not possible to state that the arbitral award would be beyond the scope of submission to arbitration if otherwise the aforesaid misinterpretation (which would include going beyond the terms of the contract), could be said to have been fairly comprehended as “disputes” within the arbitration agreement, or which were referred to the decision of the arbitrators as understood by the authorities above. If an arbitrator is alleged to have wandered outside the contract and dealt with matters not allotted to him, this would be a jurisdictional error which could be corrected on the ground of “patent illegality”, which would not apply to international commercial arbitrations that are decided under Part II of the 1996 Act. To bring in by the backdoor grounds relatable to Section 28(3) of the 1996 Act to be matters beyond the scope of submission to arbitration under Section 34(2)(a)(iv) would not be permissible as this ground must be construed narrowly and so construed, must refer only to matters which are beyond the arbitration agreement or beyond the reference to the arbitral tribunal. [Paras 42, 43] [598-H; 599-A-E] Most Basic Notions of Justice
1.9 The expression “most basic notions of … justice” finds mention in Explanation 1 to sub-clause (iii) to Section 34(2)(b). A B C D E F G H 532 SUPREME COURT REPORTS [2019] 7 S.C.R. Here again, what is referred to is, substantively or procedurally, some fundamental principle of justice which has been breached, and which shocks the conscience of the Court. The government guidelines that were referred to and strongly relied upon by the majority award to arrive at the linking factor were never in evidence before the Tribunal. In fact, the Tribunal relied upon the said guidelines by itself and states that they are to be found on a certain website. These guidelines were never, in fact, disclosed in the arbitration proceedings. The appellant would be directly affected as it would otherwise be unable to present its case, not being allowed to comment on the applicability or interpretation of those guidelines. For example, the appellant could have argued, without prejudice to the argument that linking is de hors the contract, that of the three methods for linking the New Series with the Old Series, either the second or the third method would be preferable to the first method, which the majority award has applied on its own. For this reason, the majority award needs to be set aside under Section 34(2)(a)(iii). [Paras 44-46] [599-E-F; 604-B-F]
1.10 Insofar as the argument that a new contract had been made by the majority award for the parties, without the consent of the appellant, by applying a formula outside the agreement, as per the Circular dated 15.02.2013, which itself could not be applied without the appellant’s consent, this ground under Section 34(2)(a)(iv) would not be available. The appellant argued before the arbitral tribunal that a new contract was being made by applying the formula outside what was prescribed, which was answered by the respondent, stating that it would not be possible to apply the old formula without a linking factor which would have to be introduced. Considering that the parties were at issue on this, the dispute as to whether the linking factor applied, thanks to the Circular dated 15.02.2013, is clearly something raised and argued by the parties, and is certainly something which would fall within the arbitration clause or the reference to arbitration that governs the parties. This being the case, this argument would not obtain and Section 34(2)(a)(iv), as a result, would not be attracted. However, when it comes to the public policy of India argument based upon “most basic notions of justice”, it is clear A B C D E F G H SSANGYONG ENG. & CONST. CO. LTD. v. NATIONAL HIGHWAYS AUTH. OF INDIA (NHAI) 533 that this ground can be attracted only in very exceptional circumstances when the conscience of the Court is shocked by infraction of fundamental notions or principles of justice. The formula that was applied by the agreement continued to be applied till February, 2013 – in short, it is not correct to say that the formula under the agreement could not be applied in view of the Ministry’s change in the base indices from 1993-94 to 2004-05. Further, in order to apply a linking factor, a Circular, unilaterally issued by one party, cannot possibly bind the other party to the agreement without that other party’s consent. Indeed, the Circular itself expressly stipulates that it cannot apply unless the contractors furnish an undertaking/affidavit that the price adjustment under the Circular is acceptable to them. The appellant gave such undertaking only conditionally and without prejudice to its argument that the Circular does not and cannot apply. This being the case, it is clear that the majority award created a new contract for the parties by applying the said unilateral Circular and by substituting a workable formula under the agreement by another formula de hors the agreement. This being the case, a fundamental principle of justice has been breached, namely, that a unilateral addition or alteration of a contract can never be foisted upon an unwilling party, nor can a party to the agreement be liable to perform a bargain not entered into with the other party. Clearly, such a course of conduct would be contrary to fundamental principles of justice as followed in this country, and shocks the conscience of this Court. However, this ground is available only in very exceptional circumstances, such as the fact situation in the present case. Under no circumstance can any Court interfere with an arbitral award on the ground that justice has not been done in the opinion of the Court. That would be an entry into the merits of the dispute which is contrary to the ethos of Section 34 of the 1996 Act. The judgments of the Single Judge and of the Division Bench of the Delhi High Court are set aside. Consequently, the majority award is also set aside. Under the Scheme of Section 34 of the 1996 Act, the disputes that were decided by the majority award would have to be referred afresh to another arbitration. This would cause considerable delay and be contrary to one of the important objectives of the 1996 Act, namely, speedy resolution of disputes A B C D E F G H 534 SUPREME COURT REPORTS [2019] 7 S.C.R. by the arbitral process under the Act. Therefore, in order to do complete justice between the parties, invoking power under Article 142 of the Constitution of India, and given the fact that there is a minority award which awards the appellant its claim based upon the formula mentioned in the agreement between the parties, the minority award, is upheld and it is this award, together with interest, that will now be executed between the parties. Given the reliefs claimed by the appellant in their statement of claim before the learned arbitrators, what is awarded to the appellant is the principal sum of INR 2,01,42,827/- towards price adjustment payable under sub-clause 70.3 of the contract, for the work done under the contract from September 2010 to May 2014, as well as interest at the rate of 10%, compounded monthly from the due date of payment to the date of the award, i.e., 02.05.2016, plus future interest at the rate of 12% per annum (simple) till the date of payment. [Paras 47-49] [604-G-H; 605-A-H; 606-A-F]
Questions this judgment answers
What did the Court decide in this case?
The Court recorded the following disposition: The appeal is allowed in the aforesaid terms
Which statutory provisions did this judgment involve?
Arbitration and Conciliation Act, 1996 — ss. 9, 18, 34, 34(2)(a)(iii); Constitution of India — art. 142; Foreign Awards (Recognition and Enforcement) Act, 1961 — s. 7(1)(b)(ii); Amendment Act, 2015; Arbitration and Conciliation (Amendment) Act, 2015; Applicability of the Arbitration and Conciliation (Amendment) Act, 2015.
Precedent status how later indexed judgments have treated this case
No known negative treatment found in the Courts & Cases corpus.
Another 1 relationship is under human verification and not counted above.
This is a result about the indexed corpus, not a finding that the judgment remains good law. Coverage may be incomplete.
Later judgments that treat this case
- Cited2023_11_86_94